Table 1: The activities and stages for the house construction project, starting from the preparatory work/site work, to the fencing work, including duration, optimistic and pessimistic estimates (a, b) and predecessors.
S/N |
Activity |
i - j |
Description |
Duration (in days) |
a, b (in days) |
Predecessor |
1 |
A |
2-Jan |
Site work |
5 |
3, 7 |
- |
2 |
B |
3-Feb |
Excavation work |
7 |
4, 10 |
A |
3 |
C |
4-Mar |
Foundation work |
12 |
10, 14 |
B |
4 |
D |
6-Apr |
Column structure work |
14 |
13, 15 |
C |
5 |
E |
5-Apr |
Sloof works |
8 |
5, 11 |
C |
6 |
F |
8-May |
Wall & Frame works |
14 |
12, 16 |
E |
7 |
G |
7-Jun |
Roof trust works |
12 |
8, 16 |
D |
8 |
H |
9-Jul |
Roof (Ceiling & Tiles) works |
19 |
12, 20 |
G |
9 |
I |
10-Sep |
Sanitary works and Electrical installation |
22 |
14, 24 |
F, H |
10 |
J |
11-Sep |
Plastering works |
27 |
24, 30 |
F, H |
11 |
K |
11-Oct |
Floor works |
20 |
16, 30 |
I |
12 |
L |
12-Aug |
Installation works (lamps, glass, doors, etc.) |
17 |
16, 24 |
F |
13 |
M |
13-Nov |
Painting works |
32 |
30, 24 |
J, K |
14 |
N |
13-Dec |
Fencing works |
12 |
10, 14 |
L |
15 |
O |
13-14 |
Complementary works |
8 |
6, 10 |
M, N |